Councilmembers Taylor and Schmidt,
Congratulations on your appointment to the Parkline Development Agreement Ad Hoc Subcommittee. We look forward to your strong voices in the Development Agreement negotiations for this 61-acre project
Related to the mechanics of the process:
1. How will the City arrange for community meetings so that the public can provide input to directly to Councilmembers and staff, in person?
2. How will youth voices in our community be included in the discussion?
3. How will the public be able to see what is being proposed by the Subcommittee, and the counter proposals from the developer, and the ongoing progress?
The community is looking for support for our youth:
1. Multi-purpose recreational sports field for youth - Regulation size (360 ft L x 225 ft W), programmed through the City, turf, lighted
2. Reikes style community center
The negotiations for the 59-acre Willow Village Development Agreement were transparent to the public. Below are the Willow Village amenities with a value of $180 million dollars, and the Parkline amenities which as you know are to-be-negotiated. This information is available on the Citys Willow Village webpage.
Thank you so much. Andrew Barnes. Menlo Park
Willow Village Development Agreement
Signed 12-13-22
Willow Village
SRI/Parkline
Developer Proposal
ARTICLE 5, Page 25
COMMUNITY AMENITIES; PUBLIC BENEFITS; TERMS REGARDING MAINTENANCE AND COMPLETION OF PROJECT IMPROVEMENTS
Section 5 .1, Page 26
Bonus Development Community Amenities.
Valuation
Elevated Park Improvement Costs
$66,834,336
TBD
Grocery Store Space
$30,450,935
TBD
Grocery Store Rent subsidy
$1,972,630
TBD
Affordable Housing Contribution
$5,000,000
TBD
Air Quality and Noise Monitoring Equipment Funding
$150,000
TBD
Willow Road Feasibility Study Funding
$100,000
TBD
Job Training Funding and Community Hub.
$8,304,907
TBD
Teacher Housing Rent Subsidies
$1,745,319
TBD
Bayfront Shuttle
$9,700,000
TBD
Bank
$1,557,964
TBD
Dining Venues
$10,316,257
TBD
Community Entertainment
$12,247,793
TBD
Pharmacy
$992,340
TBD
Town Square
$15,517,431
TBD
Excess Publicly Accessible Open Space
$18,078,137
TBD
TOTAL
$182,968,049
TBD
Section 5.3, Page 30
Public Benefits.
Ongoing Job Training
TBD
Career Experience Program
TBD
Dumbarton Rail
TBD
Dumbarton Forward
TBD
Bus Access
TBD
Community Use of Publicly Accessible Open Space
TBD
Gap Payment
TBD
Willow Road Tunnel
TBD
Community Use of MCS
TBD
Generators
TBD
Reduction of Daily Office Trips
TBD
Section 5.4 Maintenance of Publicly Accessible Open Space.
Section 5.5 Maintenance of Elevated Park Segment Over Willow Road and Willow Road Tunnel.
Section 5.6 Sales Tax Point of Sale Designation.
Section 5.7 BMR Housing True Up Payment.
Section 5. 8 Hamilton A venue Realignment.